Some news on the Tiny House construction front, yesterday and today… Over the weekend, the subfloor support framing got completed, for the front half of the trailer. The galvalume sheet metal underneath the floor joists was secured to the joists with screws from below, shortly after 10 “blocking” pieces were inserted between the joists to keep them straight and stable. The holes in the sheet metal for the… View More
oops
Although we had been very meticulous about checking the trailer and subfloor for squareness by measuring full-length diagonals across it, we didn’t - for whatever reasons - do likewise with the raised framing walls. I think we were lulled into some complacency by several things: (1) the fact that the floor kept appearing to be… View More